2017-716 Report – Ferriere Nord Spa v European Commission

Court Court of Justice
Date of ruling 3 November 2017
Case name (short version)
Ferriere Nord SpA v European Commission
Case Citation Case C-88/15 P

ECLI:EU:C:2017:716

Key words Appeal — Agreements, decisions and concerted practices — Italian producers of reinforcing bars — Fixing of prices and limiting and controlling output and sales — Infringement of Article 65 CS — Annulment of the initial decision by the General Court of the European Union — Decision re-adopted on the basis of Regulation (EC) No 1/2003 — Failure to issue a new statement of objections — Lack of a hearing following the annulment of the initial decision
Basic context By its appeal, Ferriere Nord SpA asks the Court to set aside the judgment of the General Court of the European Union of 9 December 2014, Ferriere Nord v Commission (T‑90/10, not published, EU:T:2014:1035, ‘the judgment under appeal’) by which the latter dismissed its action for annulment of Commission Decision C(2009) 7492 final of 30 September 2009 relating to a breach of Article 65 of the ECSC Treaty (COMP/37.956 — Reinforcing bars, re-adoption, ‘the decision of 30 September 2009’), as amended by Commission Decision C(2009) 9912 final of 8 December 2009 (‘the amending decision’) (the decision of 30 September 2009, as amended by the amending decision, ‘the decision at issue’).
Points arising – admissibility
Points arising – substance The second ground of appeal

37      In this case, as the decision at issue was adopted on the basis of Article 7(1) and Article 23(2) of Regulation No 1/2003, the procedure leading to that decision had to be conducted in accordance with that regulation and Regulation No 773/2004, the legal basis of which is Regulation No 1/2003 (see, to that effect, judgment of 29 March 2011, ThyssenKrupp Nirosta v Commission, C‑352/09 P, EU:C:2011:191, paragraph 90), despite the fact that the procedure had been initiated before Regulation No 1/2003 came into force.

42      In this connection, the General Court was entitled to refer to paragraph 73 of the judgment of 15 October 2002, Limburgse Vinyl Maatschappij and Others v Commission (C‑238/99 P, C‑244/99 P, C‑245/99 P, C‑247/99 P, C‑250/99 P to C‑252/99 P and C‑254/99 P, EU:C:2002:582), in which it is noted that the annulment of an EU measure does not necessarily affect the preparatory acts, and the procedure for replacing such a measure may, in principle, be resumed at the very point at which the illegality occurred.

43      As the General Court noted in paragraph 119 of the judgment under appeal, the 2002 decision was annulled on the ground that the Commission did not have power to adopt it on the basis of the ECSC Treaty, which was no longer in force at the date of adoption of the decision, such that it was on that exact date that the illegality occurred. As a result, that annulment did not affect the statement of objections nor the supplementary statement of objections.

44      As a result, the General Court did not make an error of law in concluding, in paragraph 122 of the judgment under appeal, that the Commission was not obligated to adopt a new statement of objections.

46      In this respect, it is important to note that, under the procedural rules established by Regulation No 1/2003, as made explicit in Regulation No 773/2004, it is laid down in Article 14(3) of that regulation that the competition authorities of the Member States are to be invited to participate in the oral hearing which, upon the request of the addressees of the statement of objections, is to follow the issuing of that statement.

50      Yet, according to the case-law noted in paragraphs 36 and 37 of the present judgment, when a decision is adopted on the basis of Regulation No 1/2003, the procedure resulting in that decision must conform to the procedural rules laid down by that regulation, even if the procedure began before that regulation came into force.

51      It follows that, before adopting the decision at issue, the Commission was required, in application of Articles 12 and 14 of Regulation No 773/2004, to give the parties the opportunity to develop their arguments during a hearing to which the competition authorities of the Member States were invited. Therefore, it cannot be held that the hearing of 13 June 2002, concerning the substance of the case, fulfilled the procedural requirements in relation to the adoption of a decision on the basis of Regulation No 1/2003.

53      As the Advocate General pointed out in points 56 and 57 of his Opinion, having regard to the importance, in the context of a procedure provided for by Regulations No 1/2003 and 773/2004, of holding an oral hearing to which the competition authorities of the Member States are invited, in accordance with Article 14(3) of the latter regulation, failure to hold such a hearing constitutes infringement of an essential procedural requirement.

54      In so far as the right to such a hearing, provided for by Regulation No 773/2004, was not respected, it is not necessary for the undertaking, the rights of which have been infringed in this way, to demonstrate that such infringement might have influenced the course of the proceedings and the content of the decision at issue to its detriment.

55      Accordingly, the procedure is necessarily vitiated, regardless of any possible detrimental consequences for Ferriere Nord that could result from that infringement (see, to that effect, judgments of 6 November 2012, Commission v Éditions Odile Jacob, C‑553/10 P and C‑554/10 P, EU:C:2012:682, paragraphs 46 to 52, and of 9 June 2016, CEPSA v Commission, C‑608/13 P, EU:C:2016:414, paragraph 36).

 

 

Intervention
Interim measures
Order 1.      Sets aside the judgment of the General Court of the European Union of 9 December 2014, Ferriere Nord v Commission (T‑90/10, not published, EU:T:2014:1035);

2.      Annuls Commission Decision C(2009) 7492 final of 30 September 2009 relating to a proceeding under Article 65 CS (Case COMP/37.956 — Reinforcing bars, re-adoption), as amended by Commission Decision C(2009) 9912 final of 8 December 2009, in so far as it concerns Ferriere Nord SpA;

3.      Orders the European Commission to bear its own costs and to pay those incurred by Ferriere Nord SpA both at first instance and in the present appeal.

 

Fine changed No
Case duration 31 months
Judge-rapporteur Vajda
Advocate-general Wahl
Notes on academic writings

 

Tags

Über

Picture Kiran Desai

Kiran Desai

Digest Editor

Partner, EU Competition Law Leader, EY Law, Brussels

>> Kiran’s CoRe Blog Case Digests >>

Hinterlasse eine Antwort

Zusammenhängende Posts

26. Nov 2020
Features von Daniel Mandrescu

Lithuanian Railways and Slovak Telecom – Implications for the Essential Facility Doctrine

The recent cases of Lithuanian Railways and Slovak Telekom address the matter of refusal to deal. Both cases, which do not engage in the assessment of this abuse, in fact, provide important guidance on the scope of application of the essential facility doctrine for current practice that will be covered in this post. Refusals to deal and the essential facility […]
22. Okt 2020
Features von Stefano Riela

Covid-19 and the geopolitics of the Herfindahl-Hirschman Index

The Covid-19 pandemic has revealed that trade is not a free flow whose tap globalization has turned on for good: export may be restricted due to unavailability and, as in the case of import, as part of foreign policy. What emerged as a discontinuity with the globalization of the last three decades makes the assessment of a market structure more […]
05. Nov 2020
Case Digests von Kiran Desai

2019:1025 LS Cable & System v Commission

Court Court of Justice Date of ruling 28 November 2019 Case name (short version) LS Cable & System v Commission Case Citation Case C-596/18 P ECLI:EU:C:2019:1025 Key words Appeal — Competition — Agreements, decisions and concerted practices — European market for underground and submarine power cables — Market allocation in connection with projects — Fines — Burden of proof — […]
05. Nov 2020
Case Digests von Kiran Desai

2019:966 Silec Cable and General Cable v Commission

Court Court of Justice Date of ruling 14 November 2019 Case name (short version) Silec Cable and General Cable v Commission Case Citation C-599/18 P ECLI:EU:C:2019:966 Key words Appeal — Competition — Agreements, decisions and concerted practices — European market for underground and submarine power cables — Market allocation in connection with projects — Proof of the infringement — Presumption […]
05. Nov 2020
Case Digests von Kiran Desai

2019:675 HSBC Holdings plc and Others v European Commission

Court General Court Date of ruling 24 September 2019 Case name (short version) HSBC Holdings plc and Others v European Commission Case Citation T-105/17 ECLI:EU:T:2019:675 Key words Competition — Agreements, decisions and concerted practices — Euro Interest Rate Derivatives sector — Decision establishing an infringement of Article 101 TFEU and Article 53 of the EEA Agreement — Manipulation of the […]
05. Nov 2020
Case Digests von Kiran Desai

2019:633 FVE Holýšov I s. r. o. and Others v European Commission

Court General Court Date of ruling 20 September 2019 Case name (short version) FVE Holýšov I s. r. o. and Others v European Commission Case Citation T-217/17 ECLI:EU:T:2019:633 Key words State aid — Market for electricity generated from renewable sources — Measures setting a minimum purchase price for electricity generated from renewable energy sources or granting a bonus to producers […]
05. Nov 2020
Case Digests von Kiran Desai

2019:532 Région Île-de-France v European Commission

Court General Court Date of ruling 12 July 2019 Case name (short version) Région Île-de-France v European Commission Case Citation T-292/17 ECLI:EU:T:2019:532 Key words State aid — Aid scheme implemented by France between 1994 and 2008 — Investment subsidies awarded by the Île-de-France Region — Decision declaring the aid scheme compatible with the internal market — Advantage — Selective nature […]
05. Nov 2020
Case Digests von Kiran Desai

2019:519 Quanta Storage, Inc. v European Commission

Court General Court Date of ruling 12 July 2019 Case name (short version) Quanta Storage, Inc. v European Commission Case Citation T-772/15 ECLI:EU:T:2019:519 Key words Competition — Agreements, decisions and concerted practices — Market for optical disk drives — Decision finding an infringement of Article 101 TFEU and Article 53 of the EEA Agreement — Collusive agreements relating to bidding […]
05. Nov 2020
Case Digests von Kiran Desai

2019:515 Sony Corporation and Sony Electronics, Inc v European Commission

Court General Court Date of ruling 12 July 2019 Case name (short version) Sony Corporation and Sony Electronics, Inc v European Commission Case Citation T-762/15 ECLI:EU:T:2019:515 Key words Competition — Agreements, decisions and concerted practices — Market for optical disk drives — Decision finding an infringement of Article 101 TFEU and Article 53 of the EEA Agreement — Collusive agreements […]
05. Nov 2020
Case Digests von Kiran Desai

2019:514 Hitachi-LG Data Storage, Inc. and Hitachi-LG Data Storage Korea, Inc. v European Commission

Court General Court Date of ruling  12 July 2019 Case name (short version) Hitachi-LG Data Storage, Inc. and Hitachi-LG Data Storage Korea, Inc. v European Commission Case Citation  T-1/16 ECLI:EU:T:2019:514 Key words Competition — Agreements, decisions and concerted practices — Market for optical disk drives — Decision finding an infringement of Article 101 TFEU and Article 53 of the EEA […]

Nutzen Sie unseren Newsletter, um sich regelmäßig über Konferenzen, Workshops, Trainings und die  neuesten Ausgaben unserer Fachzeitschriften u.a. aus den Bereichen des europäischen Wettbewerbs- und Vergaberechte, Datenschutzrechte, Abfallrecht, Umwelt- und Planungsrecht sowie Chemikalien- und Pharmarecht zu informieren.

Verpassen Sie keine Events und Publikationen. Neuigkeiten abonnieren