State aid up to 100% of the funding gap of a project can be compatible with the internal market. Introduction The European Commission approved investment aid for a Liquefied Natural Gas [LNG] terminal in Alexandroupolis in northern Greece [case SA.55526]. The project involves the following: A Floating Storage Regasification Unit [FSRU] for the storage and regasification of LNG. The construction […]
State Aid Law
Blog
State Aid Uncovered Blog
In Lexxion’s State Aid Uncovered blog, Prof. Phedon Nicolaides publishes weekly critical analyses of recent State aid judgments and decisions. Each post presents the key points of a court judgment or EU Commission decision, places it in the context of similar case law or practice, assesses the underlying reasoning and highlights any inconsistencies or contradictions.
Guest contributions from other State aid experts will also be published on the blog at irregular intervals to complement the content of the blog posts.
- WACC ×
4. January 2022 |
State Aid Uncovered
by Phedon Nicolaides
12. August 2014 |
State Aid Uncovered
by Phedon Nicolaides
Competitive selection of the operator of an infrastructural facility normally eliminates State aid. However, modifications to the contract after the operator is selected may confer an advantage that constitutes State aid. Public funding that is calculated on the basis of the “funding gap” method ensures that the aid is necessary and proportional. Introduction Several recent articles in the blog […]
- WACC ×
4. January 2022 |
State Aid Uncovered
by Phedon Nicolaides
State aid up to 100% of the funding gap of a project can be compatible with the internal market. Introduction The European Commission approved investment aid for a Liquefied Natural Gas [LNG] terminal in Alexandroupolis in northern Greece [case SA.55526]. The project involves the following: A Floating Storage Regasification Unit [FSRU] for the storage and regasification of LNG. The construction […]
12. August 2014 |
State Aid Uncovered
by Phedon Nicolaides
Competitive selection of the operator of an infrastructural facility normally eliminates State aid. However, modifications to the contract after the operator is selected may confer an advantage that constitutes State aid. Public funding that is calculated on the basis of the “funding gap” method ensures that the aid is necessary and proportional. Introduction Several recent articles in the blog […]
- WACC ×
4. January 2022 |
State Aid Uncovered
by Phedon Nicolaides
State aid up to 100% of the funding gap of a project can be compatible with the internal market. Introduction The European Commission approved investment aid for a Liquefied Natural Gas [LNG] terminal in Alexandroupolis in northern Greece [case SA.55526]. The project involves the following: A Floating Storage Regasification Unit [FSRU] for the storage and regasification of LNG. The construction […]
12. August 2014 |
State Aid Uncovered
by Phedon Nicolaides
Competitive selection of the operator of an infrastructural facility normally eliminates State aid. However, modifications to the contract after the operator is selected may confer an advantage that constitutes State aid. Public funding that is calculated on the basis of the “funding gap” method ensures that the aid is necessary and proportional. Introduction Several recent articles in the blog […]